Home » Between The Lines » Delhi High Court: Arbitrator can award compensation on guesswork when loss is difficult to prove, subject to maximum amount payable under liquidated damages clause

DISCLAIMER: The material contained in this publication is solely for information and general guidance and not for advertising or soliciting. The information provided does not constitute professional advice that may be required before acting on any matter. While every care has been taken in the preparation of this publication to ensure its accuracy, Vaish Associates Advocates neither assumes responsibility for any errors, which despite all precautions, may be found herein nor accepts any liability, and disclaims all responsibility, for any kind of loss or damage arising on account of anyone acting / refraining to act by placing reliance upon the information contained in this publication.

In the matter of Cobra Instalaciones Y Servicios, S.A. and Shyam Indus Power Solution Private Limited (J.V.) v. Haryana Vidyut Prasaran Nigam Limited [FAO(OS) (COMM) 195/2022 and CMAPPL 32865/2022] decided on April 10, 2024, the Division Bench of Delhi High Court (“Delhi HC”) has held that an Arbitrator can award compensation on guesswork when loss is difficult to prove, subject to maximum amount payable under liquidated damages clause.

Facts

Cobra Instalaciones Y Servicios, S.A. and Shyam Indus Power Solution Private Limited (J.V.) (“Appellant”) and Haryana Vidyut Prasaran Nigam Limited (“Respondent”) had entered into five contracts and subsequently, disputes arose between the parties in respect of all the five contracts. The present dispute arose in relation to contract having project number G09. For Project G09, the Government of India had obtained a loan from the International Bank for Reconstruction and Development to improve the infrastructure and power situation in the State of Haryana and the project was named as Haryana Power System Improvement Project. For the aforesaid project, pursuant to invitation of bids on May 26, 2011, the Appellant participated in the bid tender process and submitted its bid on August 6, 2011 towards procurement of plant, design, supply and installation of sub-stations and bays. Accordingly, work on the project commenced on April 8, 2012, which had to be completed within 450 days from commencement of work.

However, there was delay on part of the Appellant in execution of the project and on June 20, 2013, the Appellant had addressed a communication to the Respondent seeking deferment on imposition of liquidated damages. The Respondent addressed a letter dated July 26, 2013 to the Appellant and stated that it would defer 80 percent of the imposable liquidated damages till December 31, 2013, however, without prejudice to its rights under the contract. Thereafter, the Appellant addressed a letter dated November 3, 2014 to the Respondent, whereby the Appellant stated that liquidated damages could not be invoked because the Respondent has not suffered any actual loss. Further, the Appellant also requested the Respondent to condone the delay and extend the time period for completion of the project.

Thereafter, request made by Appellant for extension of time was withdrawn by way of communication dated September 10, 2016 on the ground that a fresh request shall be made along with placing additional facts. However, no immediate request for extension was made by the Appellant.

On November 4, 2016, the Appellant invoked arbitration agreement in terms of Clause 46.5(b) of General Conditions of the Contract (“GCC”) and Clause 26 of Particular Condition (“PC”). Upon lack of consensus between the parties on choice of arbitrator, the Appellant approached the Delhi HC seeking appointment of arbitrator under Section 11 (Appointment of arbitrators) of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”).

Another request was made for extension of time by the Appellant on April 24, 2018 in respect of two sub-stations namely Naneola and Sonta and concerning six bays. After June 27, 2023, the Respondent started to deduct liquidated damages from the running bills.

Accordingly, the Delhi HC passed an order dated October 25, 2018 in relation to application filed by Appellant for appointment of arbitrator, thereby appointing a sole arbitrator in respect of the project pertaining to the present case as well as in relation to the other four projects.

The Learned Arbitrator passed an arbitral award dated July 29, 2020, thereby directing a refund of 50% of the liquidated damages imposed by the Respondent. Considering that the Respondent had retained an amount of INR 7,25,01,510 towards liquidated damages, hence as per the arbitral award, the Appellant became entitled to a refund of INR 3,62,50,755. Additionally, the Learned Arbitrator also awarded interest to the tune of INR 2,27,49,710 as well as pendente lite and future interest at the rate of 9% per annum.

However, both the parties filed cross-petitions under Section 34 (Application for setting aside arbitral awards) of the Arbitration Act. Both the aforesaid petitions were disposed of by Single Bench of the Delhi HC by way of a common judgment dated April 25, 2022. The Single Bench of Delhi HC set aside the arbitral award to the extent that it related to the award of liquidated damages and interest payable thereon.

Aggrieved by the common judgment passed by the Single Bench of Delhi HC, the Appellant preferred an appeal under Section 37 (Appealable orders) of the Arbitration Act.

Issue

Whether an Arbitral Tribunal can award damages on the principles of “guesswork” and “rough and ready method” when it is not feasible to ascertain the exact quantum of damages, wherein the aggrieved party has suffered loss on account of breach of obligations by the other party in a project conceived in public interest.

Arguments

Contentions of the Appellant:

The Appellant submitted that the Respondent is not entitled to impose liquidated damages since it has not suffered any legal injury or loss. Further, it was argued that the relevant clause of the GCC dealing with liquidated damages did not provide for a genuine pre-estimate of damages.

It was further contended that liquidated damages, if calculated or quantifiable, must be proved. It was further submitted that even though the Respondent had claimed damages under various heads, it had failed to quantify the same. Further, it was not possible to quantify the losses claimed by the Respondent because other contractors were also involved in the project.

Further, the Appellant contended that the Single Bench of Delhi HC erred in holding that there was an inconsistency in the award passed by the Learned Arbitrator since on the one hand, it was observed that the Respondent failed to accurately ascertain damages and on the other hand, the Learned Arbitrator himself directed reduction in the quantum of liquidated damages to the extent of fifty percent. It was further contended that the Learned Arbitrator had concluded that the liquidated damages did not represent a genuine pre-estimate of damage or loss that the Respondent was likely to suffer in case of breach on part of the Appellant. Further, the Learned Arbitrator concluded that since a part of damages, loss or injury suffered by the Respondent is quantifiable, only fifty percent of the same could be retained. However, the Single Bench of Delhi HC failed to notice the aforesaid aspect.

Contentions of the Respondent:

The Respondent submitted that Section 37 of the Arbitration Act does not empower the court to indulge into re-appreciation of evidence. Further, the impugned judgment pronounced by the Single Bench of Delhi HC is just and reasoned and need not be set aside. Further, the Respondent contended that the Appellant is claiming refund of liquidated damages in its entirety, whereas during the course of hearing on July 27, 2022, the Appellant had indicated that the purpose and purview of appeal is restricted to seeking refund of fifty percent of the liquidated damages. Further, it is an established position that courts may either uphold or set aside the arbitral award, but are not empowered to modify the arbitral award.

It was further argued that there was a delay of 450 days on part of the Appellant in completion of the project and time was the essence of the contract. Furthermore, the Respondent has raised the issue of delay in project completion by way of multiple correspondences. Additionally, the Appellant failed to seek extension for completion of the project as per the relevant clause of the GCC. Hence, the judgment rendered by Single Bench of the Delhi HC should not be interfered with. Besides, the Respondent is a public sector undertaking and the project was undertaken with the sole purpose of benefitting the public at large.

It was contended that it is evident from the pleadings that the Respondent suffered damages. Further, the relevant clauses of the GCC and PC dealing with liquidated damages envisaged that the liquidated damages were a genuine pre-estimate of the loss that the Respondent would suffer if the Appellant would breach its obligations under the contract.

It was further contended that in the facts and circumstances of the case, the Respondent is entitled to retain hundred percent of the liquidated damages.

Observations of the Delhi HC

The Delhi HC observed that it needs to ascertain as to whether the conclusion arrived by the Learned Arbitrator in respect of liquidated damages is based on the evidence produced before him. To ascertain the afore-mentioned, the Delhi HC analysed the issues framed by the Learned Arbitrator during the course of Arbitration proceeding.

In so far as the issue whether time was the essence of contract, the Learned Arbitrator had concluded that even though, in strict sense, time was not the essence of contract, however, the Respondent had reminded the Appellant to complete the project on time. Hence, the Appellant could not have presumed that the delay caused in completion of the project would not lead to any consequences whatsoever. Further, Learned Arbitrator had recorded in the arbitral award that since several parts of the project were awarded to two or more contractors, each of the contractors who had contributed to the loss should be made liable to pay compensation on a pro rata basis.

Further, the Delhi HC observed that the Appellant failed to complete the project within the stipulated time period of 450 days. Further, the Appellant failed to place on record any such evidence so as to prove that it had sought extension of time for completion of the project in the manner as stipulated under the relevant clause of GCC. Even though the Learned Arbitrator had held that the Respondent had suffered loss because of delay attributable to the Appellant, however, did not conclude that the liquidated damages clause represented a genuine pre-estimate of damages that the Respondent would suffer in the event of breach of obligations on part of the Appellant. Further, the Delhi HC observed that the Learned Arbitrator had concluded that it is not possible to ascertain the exact amount of loss as attributable to each contractor, however, the burden of loss had to be shared on pro rata basis. After taking into account all relevant information, the Learned Arbitrator had concluded that the Respondent had not quantified the loss suffered by it due to delay attributable to the Appellant.

After analysing the observations made by the Learned Arbitrator, it was held that the Single Bench of Delhi HC erred in holding that there is inconsistency in the findings of the Learned Arbitrator. It is further observed that since it was not feasible to quantify losses pertaining to most of the categories, it is in such backdrop that the Learned Arbitrator adopted the methodology enunciated by the Supreme Court (“SC”) in the matter of Construction and Design Services v. Delhi Development Authority [(2015) 14 SCC 263] (“Construction and Design Services Case”), whereby a “rough and ready method” could be applied by awarding liquidated damages to the Respondent. In the aforesaid judgment, SC held that damages should be borne by the disputants in equal measure since it was difficult, if not impossible, to quantify damages.

In view of the aforesaid, the Delhi HC observed that the Single Bench of Delhi HC had wrongly concluded that since Construction and Design Services case used the expression “guesswork”, such methodology could not be adopted by courts other than the SC. In this regard, the SC had made no such observation and instead had concluded that once the Learned Arbitrator finds that liquidated damages did not represent a genuine pre-estimate of damages and the aggrieved party has suffered loss on account of breach of obligations by the other party in a project conceived in public interest, the aggrieved party would be entitled to a reasonable compensation, subject to maximum amount payable under liquidated damages clause. In such circumstances, it is the ideal approach to proceed on “guesswork” with regard to quantum of compensation to be allowed to the aggrieved party.

However, in the present case, the Learned Arbitrator did not conclude that the entire amount calculable as per the relevant clauses of the contract represented a genuine pre-estimate of damages which the Respondent could incur if the Appellant committed a breach. Therefore, it was observed by the Delhi HC that the Learned Arbitrator was entitled to apply “rough and ready method” for awarding a reasonable compensation towards losses suffered by the Respondent.

Further, the Single Bench of Delhi HC had observed that the Learned Arbitrator had not taken into account other similar contracts wherein the Respondent had not levied liquidated damages. However, it was observed by the Delhi HC that the aforesaid factor is not relevant since a project is executed based on the terms and conditions provided in the contract and in the facts and circumstances of the present case, rough and ready method / guesswork approach is available to the Learned Arbitrator.

The Delhi HC observed that the underlying rationale is that as long as there is material available that damages have been suffered by the aggrieved party, even though it is not possible to have insight into granular details, the Learned Arbitrator is entitled to employ the approach of honest guesswork and/or a rough and ready method for quantifying damages. Therefore, the Single Bench of Delhi HC erred in setting aside the arbitral award on the aforesaid ground. Further, the Delhi HC observed that upon a careful perusal, there is no inconsistency in the arbitral award. Furthermore, the Delhi HC observed that the Single Bench of Delhi HC could have either upheld or set aside the arbitral award, however, there is no power under Section 34 of the Arbitration Act to relegate the parties to the Arbitral Tribunal to agitate the dispute afresh.

Decision of the Delhi HC

In view of the facts and contentions set out hereinabove, the Delhi HC was pleased to allow the appeal partly, set aside the impugned judgment and restore the position concerning liquidated damages as was provided in the arbitral award. Hence, it was held that disputants will share the burden of liquidated damages in equal measure. Accordingly, it was directed that the Appellant would be entitled to a refund of fifty percent of liquidated damages retained by the Respondent along with interest as provided in the arbitral award.

VA View:

In the present judgment, the Delhi HC relied upon the Construction and Design Services Case decided by the SC and upheld the principle of quantification of loss done by the Arbitral Tribunal by following the principle of “honest guesswork”. In other words, once the Learned Arbitrator finds that liquidated damages did not represent a genuine pre-estimate of damages and the aggrieved party has suffered loss on account of breach of obligations by the other party in a project conceived in public interest, the aggrieved party would be entitled to a reasonable compensation, subject to maximum amount payable under liquidated damages clause. In such circumstances, it is the ideal approach to proceed on “guesswork” with regard to quantum of compensation to be allowed to the aggrieved party.

Hence, the Delhi HC reiterated the well-established principle of honest guesswork decided by the SC in the Construction and Design Services Case, which is a practical and pragmatic method to calculate damages and render justice to the aggrieved party.

For any query, please write to Mr. Bomi Daruwala at [email protected]

DOWNLOAD PDF FILE